top of page
  • Writer's picturePTA

What is Gateway 2 Levy and How it Will Be Taxed?

Introduction to Gateway 2 Levy

The Gateway 2 Levy is a crucial component of the UK's Building Safety Act 2022, specifically designed to enhance the safety of high-rise residential buildings. This levy is part of a broader set of regulations introduced in response to the Grenfell Tower tragedy, which highlighted significant flaws in building safety practices. Gateway 2, within this framework, represents the stage where developers must obtain building control approval from the Building Safety Regulator before construction can proceed. The primary aim of the Gateway 2 Levy is to ensure that developers contribute to the costs of improving building safety, particularly in high-risk buildings (HRBs) that are 18 meters or more in height or have at least seven stories.


What is Gateway 2 Levy


The Building Safety Act 2022 and the Gateway Regime

The Building Safety Act 2022 established a more stringent regulatory framework for the construction and management of high-risk buildings in the UK. The Act introduced three critical "Gateways" that serve as checkpoints throughout the lifecycle of a high-rise building:


  1. Gateway 1 (Planning Permission): This stage involves obtaining planning permission, where developers must submit detailed fire and structural safety reports as part of their application.

  2. Gateway 2 (Building Control Certification): This is the focus of our discussion and involves obtaining building control certification before construction can begin.

  3. Gateway 3 (Pre-Occupation Approval): The final stage before a building can be occupied, ensuring all safety measures are in place.


The Purpose and Scope of Gateway 2 Levy

The Gateway 2 Levy specifically targets the second stage of the building process. It is imposed when a developer applies for building control approval to start construction on a high-risk building. This levy serves two primary purposes:


  1. Funding Safety Improvements: The levy generates revenue to fund safety improvements in high-rise buildings, particularly the removal of unsafe cladding—a key issue highlighted by the Grenfell Tower fire.

  2. Encouraging Compliance: By imposing financial costs at the Gateway 2 stage, the levy encourages developers to prioritize safety from the outset, ensuring that all necessary precautions are in place before construction begins.


The levy applies only to developments in England that meet specific criteria, such as high-rise residential buildings, care homes, and hospitals. However, there are exemptions for certain types of developments, including affordable housing projects and refurbishments, to avoid disincentivizing essential building work.


How the Gateway 2 Levy is Calculated

The calculation of the Gateway 2 Levy is designed to be transparent and straightforward. The government has proposed two primary methods for determining the levy amount:


  1. Per Square Meter Charge: A fee based on the total floor area of the development. This method considers the size of the building as a proxy for potential risk and the resources required for safety compliance.

  2. Per Residential Unit Fee: Alternatively, the levy could be calculated based on the number of residential units in the development, with adjustments made for geographical disparities in property values.


The actual rate of the levy and the final method of calculation are expected to be set out in secondary legislation, with the flexibility to adjust over time as the building safety landscape evolves.


The Role of the Building Safety Regulator

At the heart of the Gateway 2 process is the Building Safety Regulator, a body established by the Building Safety Act to oversee the safety of high-risk buildings. The regulator is responsible for reviewing and approving applications at Gateway 2, ensuring that all safety requirements are met before construction can commence.

Developers must submit detailed plans and safety measures as part of their application. These documents include fire safety systems, structural integrity plans, and cladding specifications, all of which are scrutinized by the regulator. Only after the regulator is satisfied that the building will meet the necessary safety standards can construction proceed.


Costs and Implications for Developers

The introduction of the Gateway 2 Levy, alongside other safety regulations, represents a significant shift in the financial and regulatory landscape for developers. The levy adds to the costs of development, particularly in high-risk buildings, where safety requirements are most stringent.


However, these costs are deemed necessary to prevent future tragedies and ensure that new high-rise buildings in the UK are safe for residents. The government has emphasized the importance of balancing the need for safety with the potential impact on housing supply and development viability. To this end, measures have been proposed to allow small and medium-sized enterprises (SMEs) to pay the levy in instalments, ensuring that the financial burden does not stifle smaller developers.


The Gateway 2 Levy is a critical element of the UK's efforts to enhance building safety in the wake of the Grenfell Tower fire. By imposing a financial cost on developers at a crucial stage in the building process, the levy aims to ensure that safety is prioritized from the very beginning of a building's lifecycle. In the next part of this article, we will delve deeper into the specific requirements and processes involved in obtaining Gateway 2 approval, as well as the broader implications of the levy for the construction industry and housing market in the UK.



The Application Process and Key Requirements

Building on the introduction to Gateway 2 Levy, this section delves into the specifics of the application process, the key documents required, and the broader implications for the construction industry in the UK. This part of the article will provide a detailed look at how developers navigate the Gateway 2 process, the role of the Building Safety Regulator, and the potential challenges and controversies that have emerged since the introduction of the levy.


The Gateway 2 Application Process

The Gateway 2 process is one of the most critical stages in the construction of high-risk buildings (HRBs) in the UK. It represents the point at which developers must secure building control approval from the Building Safety Regulator before they can commence construction. The process is rigorous and designed to ensure that all safety measures are thoroughly planned and that the building will meet the stringent standards set out in the Building Safety Act 2022.


1. Submission of the Application

To begin the Gateway 2 process, the developer (often referred to as the "client" in regulatory terms) must submit an application to the Building Safety Regulator. This application is comprehensive and must include detailed plans and documents that demonstrate how the building will comply with all relevant safety regulations. The key components of the application include:


  • Full Plans: These are detailed architectural and structural plans that outline the building's design. They must show how the building will meet all the functional requirements of the building regulations, particularly concerning fire safety and structural integrity.

  • Safety Case Report: This document is a cornerstone of the Gateway 2 application. It details how the building will be safe for its intended use, with a particular focus on fire safety, evacuation plans, and the materials used in construction. The Safety Case Report must align with the report submitted at Gateway 1, ensuring consistency in safety planning from the design to the construction stages.

  • Competence Declaration: The developer must submit a declaration confirming that all parties involved in the construction have the necessary skills and qualifications to meet the safety standards. This declaration is part of the government's broader effort to ensure that only competent professionals are involved in high-risk building projects.

  • Construction Control Plan: This plan outlines the procedures that will be followed during construction to maintain safety and ensure compliance with the approved plans. It includes details on how construction activities will be monitored and controlled to prevent deviations from the safety protocols.

  • Fire and Emergency File: This file contains information on the fire safety systems that will be installed in the building, such as sprinkler systems, fire alarms, and emergency exits. It also includes details on how these systems will be maintained and tested throughout the building's lifecycle.


2. Review and Approval by the Building Safety Regulator

Once the application is submitted, the Building Safety Regulator conducts a thorough review. This process is not merely a formality; it involves a detailed examination of the plans and safety measures to ensure they meet the required standards. The regulator's review focuses on several key areas:


  • Fire Safety Compliance: The regulator assesses whether the building's design and proposed safety systems will effectively mitigate the risk of fire. This includes a review of the materials used, the layout of fire escapes, and the robustness of fire suppression systems.

  • Structural Integrity: The building's structural plans are scrutinized to ensure they will support the building's intended use without compromising safety. This includes evaluating the building's foundation, load-bearing elements, and resistance to natural disasters such as earthquakes.

  • Cladding and External Wall Systems: In the wake of the Grenfell Tower disaster, cladding has become a focal point of safety regulations. The regulator pays particular attention to the materials used for cladding and external walls to ensure they are non-combustible and meet the highest safety standards.


The review process can be lengthy, depending on the complexity of the project and the completeness of the application. The Building Safety Regulator may request additional information or modifications to the plans if they do not fully meet the safety requirements. Once the regulator is satisfied with the application, they will issue a building control certificate, allowing the developer to proceed with construction.


Costs Associated with Gateway 2

The costs of the Gateway 2 Levy and associated application fees can be significant. The application fee for building control approval is £180, with additional charges for the review process. The Building Safety Regulator charges £144 per hour to review each application, which can quickly add up for large or complex projects. Moreover, if the regulator incurs additional costs, such as liaising with other authorities or third parties, these costs are passed on to the developer.


The financial burden of the Gateway 2 Levy is not limited to the application fee. Developers must also consider the costs of complying with the stringent safety standards required by the Building Safety Act. These costs can include more expensive materials, additional safety systems, and the time and resources needed to ensure that all parties involved in the construction are competent and qualified.


Challenges and Controversies Surrounding Gateway 2 Levy

Since its introduction, the Gateway 2 Levy has been the subject of significant debate within the construction industry. While the levy is widely acknowledged as a necessary step to improve building safety, it has also faced criticism on several fronts:


1. Increased Costs and Delays

One of the primary concerns raised by developers is the increased costs associated with the Gateway 2 process. The need to comply with stringent safety regulations, coupled with the costs of the levy itself, can make high-rise projects more expensive and less financially viable. This is particularly true for smaller developers, who may struggle to absorb these additional costs.


Furthermore, the rigorous review process can lead to delays in construction. If the Building Safety Regulator requires modifications to the plans or additional information, the approval process can be prolonged, potentially delaying the start of construction. These delays can have a knock-on effect on project timelines and budgets, particularly in an industry where time is often a critical factor.


2. Impact on Housing Supply

Another concern is the potential impact of the Gateway 2 Levy on housing supply. The additional costs and delays associated with the levy could discourage developers from undertaking new high-rise residential projects, particularly in areas where property values are lower. This could exacerbate the UK's existing housing crisis, particularly in urban areas where high-rise developments are often seen as a solution to housing shortages.


3. Capacity of the Building Safety Regulator

The successful implementation of the Gateway 2 process relies heavily on the capacity and resources of the Building Safety Regulator. There are concerns about whether the regulator has sufficient personnel and expertise to handle the volume of applications, particularly as the new regulations take effect. If the regulator is overwhelmed, this could lead to further delays and bottlenecks in the approval process.


The Gateway 2 Levy and the associated application process represent a significant shift in how high-risk buildings are constructed and managed in the UK. While the levy aims to improve safety and prevent future tragedies, it also presents challenges for developers, particularly in terms of cost and project timelines. In the final part of this article, we will explore the broader implications of the Gateway 2 Levy for the UK's construction industry, including potential long-term effects on building practices, housing supply, and the overall safety of the built environment. We will also discuss potential solutions and adjustments that could help balance the need for safety with the practical realities of development.



Calculation of the Gateway 2 Levy

In this final part, we will explore how the Gateway 2 Levy is calculated, the rates currently proposed, and the implications for developers in the UK. Understanding the financial impact of this levy is crucial for developers as they navigate the regulatory environment set by the Building Safety Act 2022.


Calculation of the Gateway 2 Levy

The Gateway 2 Levy is intended to be both transparent and straightforward in its calculation, allowing developers to understand their financial obligations before proceeding with a project. The UK government has proposed two primary methods for calculating the levy:


Charge Per Square Meter:

  • Method: This approach calculates the levy based on the total floor area of the development. The fee is applied per square meter, making the levy proportional to the size of the building.

  • Implications: This method is particularly relevant for large developments, where the overall floor area is significant. It aligns with the principle that larger buildings, which pose more substantial risks, should contribute more to the safety fund.


Fee Per Residential Unit:

  • Method: Alternatively, the levy can be calculated based on the number of residential units within the development. This method is straightforward, applying a fixed fee for each unit.

  • Implications: This method ensures that the levy is directly tied to the number of units that will be occupied, which correlates with the potential risk to residents. It also allows for easier calculation for developments with a standard number of units per floor.


Adjustments Based on Property Value

In addition to the basic calculation methods, the levy may be adjusted to reflect disparities in property values, particularly based on geographical location. For example, developments in areas with higher property values might incur a higher levy, recognizing the increased financial capacity of developers in these regions. Conversely, developments in less affluent areas might face a lower levy to avoid discouraging investment in necessary housing projects..


Proposed Rates

While the exact rates of the Gateway 2 Levy are expected to be defined in secondary legislation, the government's consultation documents have provided some insights into the proposed charges:


  • Per Square Meter: The levy rate under this method is expected to vary depending on the type and location of the building. For instance, high-rise buildings in central urban areas might attract a higher rate compared to those in suburban or rural settings.

  • Per Residential Unit: The flat fee per unit method is designed to simplify the levy calculation for developments with a standard layout. However, this rate might also be subject to adjustments based on the building's location and overall risk profile.


The actual rates will likely be finalized after further consultation with stakeholders, including developers and housing authorities, to balance the need for safety funding with the viability of new developments.


Implications for Developers

The introduction of the Gateway 2 Levy represents a significant financial consideration for developers, particularly those involved in high-risk building projects. Developers must factor in these costs at the planning stage to ensure that their projects remain financially viable.


  • Project Viability: The levy adds to the overall cost of development, which can impact the profitability of projects, especially in areas with lower property values. Developers may need to reassess their project budgets and timelines to accommodate these additional costs.

  • Housing Supply: There is ongoing concern that the Gateway 2 Levy could reduce the number of high-rise residential projects, particularly in areas where the additional costs might make developments unprofitable. This could exacerbate existing housing shortages in some parts of the UK​ (PlanRadar).


The Gateway 2 Levy is a critical element of the UK's strategy to improve building safety in the wake of the Grenfell Tower disaster. By imposing a financial obligation on developers at a key stage in the building process, the levy aims to ensure that new high-rise buildings are constructed with the highest safety standards. However, the financial implications of the levy are significant, and developers must carefully consider these costs as part of their overall project planning. The final rates and calculation methods are still under consideration, with the government seeking to balance the need for safety funding with the economic realities of the construction industry. As these regulations continue to evolve, developers and stakeholders will need to stay informed to navigate this complex regulatory landscape effectively.



How Gateway 2 Levy Legislation is Evolving

The evolution of the Gateway 2 Levy legislation in the UK reflects a broader governmental response to improving building safety standards, particularly in the wake of high-profile incidents like the Grenfell Tower fire in 2017. As part of the Building Safety Act 2022, the Gateway 2 Levy is designed to ensure that developers contribute financially to the cost of enhancing safety in high-risk buildings. This legislation is not static; it continues to evolve as the government, industry stakeholders, and regulatory bodies adapt to the complexities of enforcing such a significant policy change. Below, we explore how this legislation is evolving, its impact on various stakeholders, and the potential future directions.


Initial Introduction and Legislative Framework

The initial introduction of the Gateway 2 Levy was part of the broader Building Safety Bill, which laid the foundation for a more stringent regulatory framework governing high-risk buildings in the UK. The primary purpose of this legislation was to address the shortcomings in building safety that had been exposed by the Grenfell Tower tragedy. The Building Safety Bill proposed the creation of a new regulatory body, the Building Safety Regulator, and introduced a series of "gateways" that developers must pass through to ensure their buildings meet safety standards at various stages of development.


The Gateway 2 Levy was conceived as a financial mechanism to support these safety measures. Specifically, it was designed to fund the removal of unsafe cladding and other critical safety improvements in high-rise residential buildings. The legislation was initially met with broad support, as it addressed a clear need for better safety in the construction of high-rise buildings. However, as the details of the legislation were fleshed out, it became apparent that the implementation of the Gateway 2 Levy would require careful consideration to avoid unintended consequences, particularly in terms of housing supply and the financial burden on developers.


Consultation and Feedback Process

One of the key aspects of the evolution of the Gateway 2 Levy legislation has been the extensive consultation process conducted by the UK government. Since the Building Safety Bill was first introduced, the government has engaged with a wide range of stakeholders, including developers, housing associations, safety experts, and the general public, to gather feedback on the proposed levy.


The consultation process has highlighted several concerns, particularly regarding the potential impact of the levy on housing supply. Developers have expressed concerns that the additional financial burden could make some projects unviable, particularly in areas with lower property values. This feedback has led the government to consider various adjustments to the legislation, including potential exemptions for certain types of developments, such as affordable housing and small-scale projects. Additionally, there has been discussion around the possibility of allowing developers to pay the levy in instalments, rather than as a lump sum, to reduce the immediate financial impact.


The consultation process also revealed a need for greater clarity on how the levy would be calculated and applied. In response, the government has provided more detailed guidance on the calculation methods, including the options for a per square meter charge or a per residential unit fee. These options allow for some flexibility in how the levy is applied, taking into account the size and location of the development.


Adjustments to the Scope and Implementation of the Levy

As the Gateway 2 Levy legislation has evolved, there have been several adjustments to its scope and implementation. Initially, the levy was proposed as a broad measure that would apply to all high-risk buildings, regardless of their specific characteristics. However, feedback from stakeholders led to the introduction of several exemptions and adjustments.


For example, the legislation now includes specific exemptions for affordable housing developments. This exemption was introduced to avoid disincentivizing the construction of affordable housing, which is already under pressure due to the high costs of land and construction. Similarly, there are provisions for exemptions or reduced rates for developments in areas with lower property values, where the financial burden of the levy could otherwise make projects unviable.


Another significant adjustment has been the introduction of payment flexibility. Recognizing that the lump-sum payment of the levy could be a significant financial hurdle for some developers, particularly small and medium-sized enterprises (SMEs), the government has introduced the option for developers to pay the levy in instalments. This change is intended to reduce the immediate financial impact on developers and ensure that the levy does not unduly hinder the development of new housing.


Evolving Regulatory Oversight and Enforcement

The role of the Building Safety Regulator has also evolved as part of the implementation of the Gateway 2 Levy. Initially, the regulator's role was primarily focused on reviewing and approving building control applications at the Gateway 2 stage. However, as the legislation has evolved, the regulator's responsibilities have expanded to include ongoing oversight of compliance with the levy and related safety standards.


This expanded role includes the ability to conduct audits and inspections to ensure that developers are meeting their obligations under the Gateway 2 Levy. The regulator is also responsible for enforcing penalties for non-compliance, which can include fines, stop notices, and other sanctions. This increased regulatory oversight is intended to ensure that the levy is effectively enforced and that the funds generated are used to improve building safety.


Future Directions and Potential Challenges

Looking forward, the evolution of the Gateway 2 Levy legislation is likely to continue as the government and industry stakeholders respond to the challenges of implementing this complex policy. One of the key areas of focus will be ensuring that the levy achieves its intended goals without unduly burdening the construction industry or exacerbating the housing crisis.


There is also the potential for further adjustments to the levy calculation methods and rates, particularly as more data becomes available on the impact of the levy on housing supply and development costs. Additionally, the government may explore other funding mechanisms or complementary policies to support building safety improvements, particularly in cases where the Gateway 2 Levy alone may not be sufficient to cover the necessary costs.​ 


Another potential challenge is ensuring that the Building Safety Regulator has the capacity and resources to effectively enforce the Gateway 2 Levy and related safety standards. As the regulator takes on an expanded role, there will be a need for ongoing investment in training, staffing, and technological tools to ensure that the regulator can meet its responsibilities effectively.


Finally, the broader context of the UK's building safety regulations is also evolving, with ongoing discussions around issues such as cladding remediation, fire safety standards, and the responsibilities of building owners and managers. The Gateway 2 Levy is just one part of this broader regulatory landscape, and its success will depend on how well it integrates with other safety measures and policies.


The Gateway 2 Levy legislation is a dynamic and evolving policy that reflects the UK government's commitment to improving building safety in the wake of the Grenfell Tower disaster. While the levy has already undergone significant changes since its introduction, it is likely to continue evolving as the government and industry stakeholders work to balance the need for safety with the practical realities of the construction industry.



FAQs


1. What types of buildings are specifically targeted by the Gateway 2 Levy?

The Gateway 2 Levy primarily targets high-risk buildings, which include residential buildings that are 18 meters or more in height or have at least seven storeys. This also covers mixed-use buildings with residential components.


2. Are commercial buildings subject to the Gateway 2 Levy?

No, the Gateway 2 Levy is specifically focused on high-risk residential buildings. Purely commercial buildings are not subject to this levy unless they are part of a mixed-use development that includes residential units.


3. How does the Gateway 2 Levy interact with the Residential Property Developer Tax (RPDT)?

The Gateway 2 Levy and the RPDT are separate but complementary taxes. The Gateway 2 Levy is applied at the building control approval stage, while the RPDT is a broader tax on profits made by developers from residential property developments.


4. Can developers appeal against the imposition of the Gateway 2 Levy?

Yes, developers can appeal if they believe the levy has been incorrectly applied. Appeals would typically be made through the relevant planning or building control authority.


5. Are there any geographic exemptions to the Gateway 2 Levy in the UK?

Currently, the Gateway 2 Levy applies across England. However, the rate might be adjusted based on the geographical location of the development, particularly to reflect disparities in property values.


6. How does the government ensure the funds from the Gateway 2 Levy are used appropriately?

The funds collected from the Gateway 2 Levy are managed by the Building Safety Regulator, which is responsible for ensuring that the funds are allocated to projects that improve building safety, such as cladding remediation.


7. Is the Gateway 2 Levy applicable to student accommodation buildings?

Yes, if the student accommodation building meets the criteria for high-risk buildings (18 meters or more in height or at least seven storeys), it is subject to the Gateway 2 Levy.


8. What is the consequence of not paying the Gateway 2 Levy?

Failure to pay the Gateway 2 Levy can result in the withholding of building control approval, which means that construction cannot legally proceed until the levy is paid.


9. Are there any subsidies or financial aid available to help developers pay the Gateway 2 Levy?

As of July 2024, there are no specific subsidies available to cover the Gateway 2 Levy. However, smaller developers may be allowed to pay the levy in instalments to ease the financial burden.


10. How does the Gateway 2 Levy affect insurance premiums for developers?

The introduction of the Gateway 2 Levy may lead to higher insurance premiums for developers, as insurers factor in the increased regulatory scrutiny and potential risks associated with high-risk buildings.


11. What is the role of the Building Safety Fund in relation to the Gateway 2 Levy?

The Building Safety Fund is a separate government initiative aimed at funding the removal of unsafe cladding. The Gateway 2 Levy contributes additional funds to support broader building safety measures.


12. Does the Gateway 2 Levy apply to existing buildings undergoing significant refurbishment?

The levy primarily applies to new developments, but it can also be imposed on existing buildings that are being significantly altered to meet the criteria of high-risk buildings.


13. Is the Gateway 2 Levy refundable if a project is canceled after payment?

If a project is canceled after the levy has been paid, refunds are not typically provided. However, this would depend on the specific terms of the payment and any agreements made with the regulatory authorities.


14. How does the Gateway 2 Levy impact the overall cost of a development project?

The levy adds to the overall cost of a project, potentially making some developments less financially viable, particularly in areas with lower property values.


15. Can the rate of the Gateway 2 Levy change during the course of a project?

Yes, the rate of the levy can be adjusted, particularly if the project scope changes significantly or if new legislation or secondary regulations are introduced during the project's lifecycle.


16. Are there any penalties for late payment of the Gateway 2 Levy?

Yes, late payment of the levy can result in fines and other penalties, including the potential suspension of construction activities until payment is made.


17. How does the Gateway 2 Levy affect small and medium-sized developers compared to large developers?

The levy can be more challenging for small and medium-sized developers due to their smaller financial resources. However, payment instalment options are available to mitigate the impact.


18. What role does local government play in the enforcement of the Gateway 2 Levy?

Local governments are involved in the enforcement of the Gateway 2 Levy through their building control departments, which work in conjunction with the Building Safety Regulator.


19. How is the Gateway 2 Levy rate determined for mixed-use developments?

For mixed-use developments, the levy is calculated based on the portion of the building that qualifies as high-risk residential. The rate may vary depending on the specific use and risk profile of the building.


20. Are there any ongoing legislative reviews that might change the Gateway 2 Levy?

Yes, the legislation is subject to ongoing review, and further adjustments to the Gateway 2 Levy, including rate changes or additional exemptions, may be introduced as part of future regulatory updates.


13 views

Comments


bottom of page